Circular No. 10 / 2013-Customs dated 6.3.2013
Sub: Post Export EPCG duty credit scrip(s) Scheme and certain other changes
related to Foreign Trade Policy 2009-14 – Reg.
Reference is made to Para 4 of Circular No.20/2012 – Customs dated 27.7.2012
wherein it was indicated that there are certain areas of change in the FTP
supplement 2012-13 for which notifications shall be issued subsequently as
modalities to make them operational were being worked out. In these areas, the
Department of Revenue has since issued notifications described below.
2. The definition of capital goods (under para 9.12 of FTP amended on 26.7.2012)
now includes catalysts for initial charge plus one subsequent charge. The
notification No.3/2013-Customs dated 13.2.13 has amended notification Nos. 100
to 103/2009- Customs to specify the conditions subject to which the catalyst for
one subsequent charge shall be allowed under EPCG Scheme. The notification
No.4/2013-Customs dated 14.2.13 has been issued amending 31 customs
notifications so as to specify Visakhapatnam Airport for making imports and
exports under the export promotion schemes.
Post Export EPCG duty credit scrip(s) Scheme
3. It may be recalled that the Post Export EPCG duty credit scrip(s) Scheme was
notified on 5.6.12 vide a new para 5.11 in FTP read with a new para 5.23 in the
HBP v1. These paras have been further amended on 26.7.12 and 8.2.13 by
Department of Commerce. These provisions may be downloaded from DGFT website and
perused. The Post Export EPCG duty credit scrips to be issued by Regional
Authority of the DGFT are intended to be used for, apart from imports of goods,
domestic procurement. Their usage pattern is intended to be similar to that
prescribed for freely transferable duty credit scrips issued by the Regional
Authorities under chapter 3 of FTP.
4. The scheme envisages that the duty credit in these scrips shall be a duty
remission computed based on the basic customs duty paid on capital goods which
had been imported on payment of all applicable duties of customs in cash.
Subject to installation and use of the imported capital goods, and other
conditions including non-disposal of the capital goods till the date of last
export, the duty remission may be granted by the Regional Authority in
proportion to export obligation fulfilled within a fixed export obligation
period. For this purpose, the export obligation would be fixed (over and above
average export obligation) at 85% of applicable specific export obligation,
computed as if the duty paid imports had taken benefit of duty exemption (i.e.
like the EPCG duty exemption schemes, either zero duty or concessional 3% duty).
As in the existing EPCG duty exemption scheme, if it is opted to not take the
Cenvat credit of additional duty of customs paid, a lower export obligation
would be fixed. There is no provision for extension of export obligation period
in this scheme.
5. The notification Nos.5/2013-Customs and 6/2013-Customs both dated 18.2.13
have been issued under section 25(1) of Customs Act, 1962 to permit imports
through debit of the customs duties in the said duty credit scrip. The
notifications are for scrip variants where export obligation is fixed like the
zero duty or concessional 3% duty EPCG scheme, respectively. The mechanisms of
fixing the export obligation, and of granting the remission, are explained in
the notifications. Further, notification Nos.2/2013-Central Excise and
3/2013-Central Excise both dated 18.2.13 have been issued under section 5A (1)
of the Central Excise Act, 1944, read section 3 (3) of the Additional Duties of
Excise (Goods of Special Importance) Act, 1957 and section 3 (3) of the
Additional Duties of Excise (Textiles and Textile Articles) Act, 1978, to permit
domestic procurement. All these four notifications are conditional
notifications. Notification No.7/2013-Customs dated 19.2.13 makes consequential
amendments in the two customs notifications for the purpose of cross referencing
the two central excise notifications.
6. As mentioned hereinabove, in this Scheme the duty remission is envisaged in
proportion to export obligation fulfilled within a fixed export obligation
period. Unlike the EPCG duty exemption schemes, the block obligation periods or
their related proportions of export obligation fulfillment are not pre-defined
in the new scheme. More than one duty credit scrip may issue (against the duty
paid import of capital goods) based on the progressive fulfillment, during the
specified export obligation period, of larger extents of the total export
obligation. The meaning of ‘export obligation’ would apply individually to each
duty credit scrip. Further, scrip issuance is akin to a discharge (or partial
discharge) of the export obligation and is a remission by the DGFT of duty
collected by the CBEC. Therefore, it is necessary that the Deputy/Assistant
Commissioner of Customs satisfies himself of the compliance of the conditions of
the notification (including fulfillment of export obligation, the quantum of
duty remission in the duty credit scrip, the cumulative duty credits issued
against imported duty paid capital goods) before allowing a duty credit scrip,
issued under the Scheme, to be registered.
7. A sequential monitoring should be followed. This begins from registration of
authorization (for importing capital goods) at the port of registration and is
followed by import on payment of full applicable duties of customs in cash,
endorsement of import particulars on authorization at time of clearance, making
specified endorsements on bill(s) of entry at time of import, ensuring
registration or installation/use of all imports under authorization before any
scrip issues, registration of scrip at the same port, keeping cumulative record
of duty credit scrips issued against an authorization, and making the indicated
endorsements on documents at the time of registration. Moreover, the assessment
Group which handles the authorization to import capital goods on payment of duty
under this variant of the EPCG scheme would need to allow the registration of
this duty credit scrip. The genuineness of the post export EPCG duty credit
scrip should be verified.
8. Safeguards are provided in the notifications relating to making endorsements
on the documents. The option for not availing Cenvat Credit on capital goods
imported under authorization and thereby enjoying a lower export obligation is
to be backed by a certification. Jurisdictional Central Excise authority should
ensure that certificate on non-availment of Cenvat Credit is issued
expeditiously and normally within two weeks but not later than four weeks under
all circumstances. Where the goods imported against an authorization are found
defective or unfit for use and are re-exported back to the foreign supplier, if
claim of duty drawback is made, no duty remission for the duty paid at the time
of import on the re-exported goods is to be allowed. Further, after any duty
remission in the form of duty credit scrip has been claimed in respect of the
duty paid on the goods imported against an authorization, no duty drawback shall
be allowed when the goods are re-exported and the export obligation is also not
to be re-fixed. Indigenous sourcing of capital goods (referred to as
invalidation procedure of import authorization) on payment of duty is not
permitted in this scheme.
9. It may also be noted that the post export EPCG duty credit scrip cannot be
issued as a refund on the premise that duty was paid but a situation arose where
there was no export obligation to be fulfilled. The Commissioners of Customs are
also to exercise special checks so as to ensure that there is no misuse of the
scheme and a proper record of all such checks is maintained. These shall include
random verifications of the address shown on the authorizations (for import of
capital goods) during their validity period in at least 10% of authorizations,
random verifications of the certificates produced (not issued by central excise
authorities) and of the declarations submitted with respect to Condition No. 14
(e)(i) of the Customs notifications in at least 10% cases. These verifications
should be made through the Commissioners of Central Excise. The central excise
authorities should include, in their verification, a check of the periodical
utility bills (containing the address) as one of the means enabling verification
of installation/ operation/ authorization holder premises. The Commissioners are
expected to exercise due diligence to prevent misuse. If any other measure or
safeguard is considered necessary it may be informed to the Board for
appropriate action. Moreover, relevant aspects should also be incorporated in
the monthly report of “Monitoring of Export/Imports under various Export
Promotion Schemes” sent to the Board in terms of letter No. 605/64/2008-DBK
dated 20.11.2008.
10. The Director General (Systems and Data Management) is to take steps to
capture relevant details of authorizations, imports made (including duties paid)
and the duty remitted against them, and in addition the subsequent utilization
of the post export EPCG duty credit scrip. Moreover, the utilization of scrip
under the Customs exemption notifications shall be shown separately in the FMR
Customs (Annexure III) and that under the Central Excise exemption notifications
shall be shown separately in the FMR Central Excise (Annexure IV) with a remark
that it is a duty remission.
11. The Commissioners should ensure that the above mentioned Customs and Central
Excise notifications and this Circular are carefully perused for details and
implementation. Suitable public notice and standing order may be issued for
guidance of the trade and officers.
Yours faithfully,
(Vinod Kumar Agrawal)
OSD (Drawback)
F.No.605/12/2012-DBK (Pt.)
|
|